Mungkin Anda memerlukan analisa AHS-SNI untuk pekerjaan penutup besi dan aluminium, seperti pasang terali besi, rolling door, pasang besi profil, perakitan baja, pengelasan dengan las listrik, kusen pintu dan jendela aluminium, dll. Inilah analisa AHS SNI tahun 2011.
ANALISA HARGA SATUAN PEKERJAAN PENUTUP BESI & ALLUMINIUM
No. | URAIAN |
SAT
|
VOLUME
|
HARGA SAT
|
HARGA
|
|
(Rp)
|
(Rp)
|
|||||
K-01 | 1 Kg Besi profil | |||||
– | Besi profil WF |
Kg
|
1.1000
|
24,000.00
|
26,400.00
|
|
– | Meni besi |
Kg
|
0.0800
|
30,400.00
|
2,432.00
|
|
– | Pekerja |
Oh
|
0.0600
|
42,000.00
|
2,520.00
|
|
– | Tukang besi |
Oh
|
0.0060
|
65,000.00
|
390.00
|
|
– | Kepala tukang |
Oh
|
0.0060
|
75,000.00
|
450.00
|
|
– | Mandor |
Oh
|
0.0003
|
80,000.00
|
24.00
|
|
Jumlah |
32,216.00
|
|||||
Dibulatkan |
32,216.00
|
|||||
K-02 | 1 Kg Perakitan baja | |||||
– | Solar |
m’
|
0.0100
|
7,150.0000
|
71.50
|
|
– | Minyak pelumas |
m’
|
0.0010
|
55,000.0000
|
55.00
|
|
– | Sewa alat |
jam
|
0.0080
|
100,000.0000
|
800.00
|
|
– | Pekerja |
Oh
|
0.0010
|
42,000.0000
|
42.00
|
|
– | Tukang besi |
Oh
|
0.00001
|
65,000.0000
|
0.65
|
|
– | Kepala tukang |
Oh
|
0.00001
|
75,000.0000
|
0.75
|
|
– | Mandor |
Oh
|
0.00005
|
80,000.0000
|
4.00
|
|
Jumlah |
973.90
|
|||||
Dibulatkan |
974.00
|
|||||
K-03 | 1 Cm Pengelasan dengan las listrik | |||||
– | kawat las |
kg
|
0.0400
|
23,600.00
|
944.00
|
|
– | Solar |
ltr
|
0.0300
|
7,150.00
|
214.50
|
|
– | Minyak pelumas |
ltr
|
0.0040
|
55,000.00
|
220.00
|
|
– | Sewa alat |
jam
|
0.0170
|
100,000.00
|
1,700.00
|
|
– | Pekerja |
org
|
0.0040
|
42,000.00
|
168.00
|
|
– | Tukang |
org
|
0.0020
|
65,000.00
|
130.00
|
|
– | Kepala Tukang |
org
|
0.0002
|
75,000.00
|
15.00
|
|
– | Mandor |
org
|
0.0002
|
80,000.00
|
16.00
|
|
Jumlah |
2,463.50
|
|||||
Dibulatkan |
2,464.00
|
|||||
K-04 | 1 m2 Pintu Rolling Door | |||||
– | Rolling door |
M2
|
1.0000
|
306,600.00
|
306,600.00
|
|
– | Pekerja |
Oh
|
1.0500
|
42,000.00
|
44,100.00
|
|
– | Tukang besi |
Oh
|
1.5000
|
65,000.00
|
97,500.00
|
|
– | Kepala tukang |
Oh
|
0.1050
|
75,000.00
|
7,875.00
|
|
– | Mandor |
Oh
|
0.0052
|
80,000.00
|
416.00
|
|
Jumlah |
456,491.00
|
|||||
Dibulatkan |
456,491.00
|
|||||
K-05 | 1 m2 Pintu Alluminium Natural | |||||
– | Pintu alluminium natural |
m2
|
1.0000
|
211,800.00
|
211,800.00
|
|
– | Pekerja |
Oh
|
1.0500
|
42,000.00
|
44,100.00
|
|
– | Tukang besi |
Oh
|
1.0500
|
65,000.00
|
68,250.00
|
|
– | Kepala tukang |
Oh
|
0.1050
|
75,000.00
|
7,875.00
|
|
– | Mandor |
Oh
|
0.0052
|
80,000.00
|
416.00
|
|
Jumlah |
332,441.00
|
|||||
Dibulatkan |
332,441.00
|
|||||
K-06 | 1 m2 Terali Besi | |||||
– | Besi strip 2 x 3 |
m’
|
11.5000
|
5,500.00
|
63,250.00
|
|
– | Pekerja |
Oh
|
1.2000
|
42,000.00
|
50,400.00
|
|
– | Tukang las |
Oh
|
1.2000
|
65,000.00
|
78,000.00
|
|
– | Kepala tukang |
Oh
|
0.0120
|
75,000.00
|
900.00
|
|
– | Mandor |
Oh
|
0.0006
|
80,000.00
|
48.00
|
|
Jumlah |
192,598.00
|
|||||
Dibulatkan |
192,598.00
|
|||||
K-07 | 1 m2 Kawat Harmonika 4 cm | |||||
– | Kawat harmonika |
M2
|
1.1000
|
35,900.00
|
39,490.00
|
|
– | Paku biasa ½” – 1″ |
kg
|
0.0200
|
23,800.00
|
476.00
|
|
– | Papan kayu kamper |
M2
|
0.0018
|
5,692,600.00
|
10,246.68
|
|
– | Pekerja |
Oh
|
0.1000
|
42,000.00
|
4,200.00
|
|
– | Tukang kayu |
Oh
|
0.1000
|
65,000.00
|
6,500.00
|
|
– | Kepala tukang |
Oh
|
0.0100
|
75,000.00
|
750.00
|
|
– | Mandor |
Oh
|
0.0050
|
80,000.00
|
400.00
|
|
Jumlah |
62,062.68
|
|||||
Dibulatkan |
62,063.00
|
|||||
K-08 | 1 m’ Talang Datar, Seng BJLS 28 lebar 90 cm | |||||
– | Seng plat 3′ x 6′ BJLS 30 |
m’
|
1.0500
|
20,801.00
|
21,841.05
|
|
– | Paku biasa ½” – 1″ |
Kg
|
0.0150
|
23,800.00
|
357.00
|
|
– | Kayu papan borneo super |
M3
|
0.0096
|
5,595,800.00
|
53,719.68
|
|
– | Flincote / meni besi |
Kg
|
0.2500
|
30,400.00
|
7,600.00
|
|
– | Pekerja |
Oh
|
0.1500
|
42,000.00
|
6,300.00
|
|
– | Tukang kayu |
Oh
|
0.4000
|
65,000.00
|
26,000.00
|
|
– | Kepala tukang |
Oh
|
0.0250
|
75,000.00
|
1,875.00
|
|
– | Mandor |
Oh
|
0.0013
|
80,000.00
|
104.00
|
|
Jumlah |
117,796.73
|
|||||
Dibulatkan |
117,797.00
|
|||||
K-09 | 1 m’ Talang Miring, Seng BJLS 28 lebar 90 cm | |||||
– | Seng plat 3′ x 6′ BJLS 30 |
m’
|
1.0500
|
20,801.00
|
21,841.05
|
|
– | Paku biasa ½” – 1″ |
Kg
|
0.0150
|
23,800.00
|
357.00
|
|
– | Kayu papan borneo super |
M3
|
0.0190
|
5,595,800.00
|
106,320.20
|
|
– | Flincote / meni besi |
Kg
|
0.3000
|
30,400.00
|
9,120.00
|
|
– | Pekerja |
Oh
|
0.2000
|
42,000.00
|
8,400.00
|
|
– | Tukang kayu |
Oh
|
0.4000
|
65,000.00
|
26,000.00
|
|
– | Kepala tukang |
Oh
|
0.0250
|
75,000.00
|
1,875.00
|
|
– | Mandor |
Oh
|
0.0013
|
80,000.00
|
100.00
|
|
Jumlah |
174,013.25
|
|||||
Dibulatkan |
174,013.00
|
|||||
K-10 | 1 m’ Talang 1/2 lingkaran D-15 cm, seng pelat BJLS 28 lebar 90 cm | |||||
– | Seng plat 3′ x 6′ BJLS 30 |
m’
|
1.0500
|
20,801.00
|
21,841.05
|
|
– | Paku biasa ½” – 1″ |
Kg
|
0.1000
|
23,800.00
|
2,380.00
|
|
– | Kayu papan borneo super |
kg
|
0.0190
|
5,595,800.00
|
106,320.20
|
|
– | Besi strip |
Kg
|
0.5000
|
26,800.00
|
13,400.00
|
|
– | Pekerja |
Oh
|
0.1500
|
42,000.00
|
6,300.00
|
|
– | Tukang kayu |
Oh
|
0.3000
|
65,000.00
|
19,500.00
|
|
– | Kepala tukang |
Oh
|
0.0300
|
75,000.00
|
2,250.00
|
|
– | Mandor |
Oh
|
0.0080
|
80,000.00
|
640.00
|
|
Jumlah |
172,631.25
|
|||||
Dibulatkan |
172,631.00
|
|||||
K-11 | 1 m’ Pasang kusen pintu/jendela alluminium natural 4″ | |||||
– | Alumunium profil natural 4″ |
m’
|
1.1000
|
151,100.00
|
166,210.00
|
|
– | Skrup fixer |
bh
|
2.0000
|
250.00
|
500.00
|
|
– | Sealant |
m’
|
1.0000
|
7,500.00
|
7,500.00
|
|
– | Pekerja |
Oh
|
0.0430
|
42,000.00
|
1,806.00
|
|
– | Tukang kayu |
Oh
|
0.0430
|
65,000.00
|
2,795.00
|
|
– | Kepala tukang |
Oh
|
0.0043
|
75,000.00
|
322.50
|
|
– | Mandor |
Oh
|
0.0021
|
80,000.00
|
168.00
|
|
Jumlah |
179,301.50
|
|||||
Dibulatkan |
179,302.00
|
|||||
K-12 | 1 m’ Pasang kusen pintu/jendela alluminium warna 4″ | |||||
– | Alumunium profil warna 4″ |
m’
|
1.1000
|
163,000.00
|
179,300.00
|
|
– | Skrup fixer |
bh
|
2.0000
|
250.00
|
500.00
|
|
– | Sealant |
m’
|
1.0000
|
7,500.00
|
7,500.00
|
|
– | Pekerja |
Oh
|
0.0430
|
42,000.00
|
1,806.00
|
|
– | Tukang kayu |
Oh
|
0.0430
|
65,000.00
|
2,795.00
|
|
– | Kepala tukang |
Oh
|
0.0043
|
75,000.00
|
322.50
|
|
– | Mandor |
Oh
|
0.0021
|
80,000.00
|
168.00
|
|
Jumlah |
192,391.50
|
|||||
Dibulatkan |
192,392.00
|
|||||
K-13 | 1 m’ Pasang kusen pintu/jendela alluminium natural 3″ | |||||
– | Alumunium profil natural 3″ |
m’
|
1.1000
|
81,000.00
|
89,100.00
|
|
– | Skrup fixer |
bh
|
2.0000
|
250.00
|
500.00
|
|
– | Sealant |
m’
|
1.0000
|
7,500.00
|
7,500.00
|
|
– | Pekerja |
Oh
|
0.0430
|
42,000.00
|
1,806.00
|
|
– | Tukang kayu |
Oh
|
0.0430
|
65,000.00
|
2,795.00
|
|
– | Kepala tukang |
Oh
|
0.0043
|
75,000.00
|
322.50
|
|
– | Mandor |
Oh
|
0.0021
|
80,000.00
|
168.00
|
|
Jumlah |
102,191.50
|
|||||
Dibulatkan |
102,192.00
|
|||||
K-14 | 1 m’ Pasang kusen pintu/jendela alluminium warna 3″ | |||||
– | Alumunium profil warna 3″ |
m’
|
1.1000
|
102,000.00
|
112,200.00
|
|
– | Skrup fixer |
bh
|
2.0000
|
250.00
|
500.00
|
|
– | Sealant |
m’
|
1.0000
|
7,500.00
|
7,500.00
|
|
– | Pekerja |
Oh
|
0.0430
|
42,000.00
|
1,806.00
|
|
– | Tukang kayu |
Oh
|
0.0430
|
65,000.00
|
2,795.00
|
|
– | Kepala tukang |
Oh
|
0.0043
|
75,000.00
|
322.50
|
|
– | Mandor |
Oh
|
0.0021
|
80,000.00
|
168.00
|
|
Jumlah |
125,291.50
|
|||||
Dibulatkan |
125,292.00
|
|||||
K-15 | 1 m2 Pintu alluminium strip lebar 8 cm | |||||
– | Alumunium profil 4″ natural |
m’
|
4.4000
|
151,100.00
|
664,840.00
|
|
– | Alumunium strip 6mm |
m2
|
1.0500
|
171,800.00
|
180,390.00
|
|
– | Pekerja |
Oh
|
0.0850
|
42,000.00
|
3,570.00
|
|
– | Tukang kayu |
Oh
|
0.0850
|
65,000.00
|
5,525.00
|
|
– | Kepala tukang |
Oh
|
0.0085
|
75,000.00
|
637.50
|
|
– | Mandor |
Oh
|
0.0042
|
80,000.00
|
336.00
|
|
Jumlah |
855,298.50
|
|||||
Dibulatkan |
855,299.00
|
|||||
K-16 | 1 m2 Pintu/jendela kaca rangka alluminium natural 4″ | |||||
– | Alumunium profil natural 4″ |
m’
|
4.4000
|
151,100.00
|
664,840.00
|
|
– | Profil alluminium T |
m’
|
4.5000
|
12,200.00
|
54,900.00
|
|
– | Sealant |
tube
|
0.2700
|
7,500.00
|
2,025.00
|
|
– | Pekerja |
Oh
|
0.0850
|
42,000.00
|
3,570.00
|
|
– | Tukang kayu |
Oh
|
0.0850
|
65,000.00
|
5,525.00
|
|
– | Kepala tukang |
Oh
|
0.0085
|
75,000.00
|
637.50
|
|
– | Mandor |
Oh
|
0.0050
|
80,000.00
|
400.00
|
|
Jumlah |
731,897.50
|
|||||
Dibulatkan |
731,898.00
|
|||||
K-17 | 1 m2 Pintu/jendela kaca rangka alluminium warna 4″ | |||||
– | Alumunium profil warna 4″ |
m’
|
4.4000
|
163,000.00
|
717,200.00
|
|
– | Profil alluminium T |
m’
|
4.5000
|
12,200.00
|
54,900.00
|
|
– | Sealant |
tube
|
0.2700
|
7,500.00
|
2,025.00
|
|
– | Pekerja |
Oh
|
0.0850
|
42,000.00
|
3,570.00
|
|
– | Tukang kayu |
Oh
|
0.0850
|
65,000.00
|
5,525.00
|
|
– | Kepala tukang |
Oh
|
0.0085
|
75,000.00
|
637.50
|
|
– | Mandor |
Oh
|
0.0050
|
80,000.00
|
400.00
|
|
Jumlah |
784,257.50
|
|||||
Dibulatkan |
784,258.00
|
|||||
K-18 | 1 m2 Jendela nako & teralis (10 klips) | |||||
– | Jendela nako (rangka + kaca 5 mm) |
m2
|
1.1000
|
300,000.00
|
330,000.00
|
|
– | Paku skrup 1cm – 2,5cm |
bh
|
10.0000
|
250.00
|
2,500.00
|
|
– | Besi strip |
m’
|
7.0000
|
5,500.00
|
38,500.00
|
|
– | Pekerja |
Oh
|
0.2000
|
42,000.00
|
8,400.00
|
|
– | Tukang kayu |
Oh
|
0.2000
|
65,000.00
|
13,000.00
|
|
– | Kepala tukang |
Oh
|
0.0200
|
75,000.00
|
1,500.00
|
|
– | Mandor |
Oh
|
0.0010
|
80,000.00
|
80.00
|
|
Jumlah |
393,980.00
|
|||||
Dibulatkan |
393,980.00
|
|||||
K-19 | 1 m2 Pintu pelat baja tebal 2mm rangkap, rangka baja siku | |||||
– | Besi siku L 30.30.3 |
Kg
|
15.0000
|
24,000.00
|
360,000.00
|
|
– | Baja pelat |
Kg
|
32.8000
|
24,000.00
|
787,200.00
|
|
– | kawat las |
Kg
|
0.0500
|
23,600.00
|
1,180.00
|
|
– | Pekerja |
Oh
|
0.2000
|
42,000.00
|
8,400.00
|
|
– | Tukang kayu |
Oh
|
0.2000
|
65,000.00
|
13,000.00
|
|
– | Kepala tukang |
Oh
|
0.0200
|
75,000.00
|
1,500.00
|
|
– | Mandor |
Oh
|
0.0010
|
80,000.00
|
80.00
|
|
Jumlah |
1,171,360.00
|
|||||
Dibulatkan |
1,171,360.00
|
|||||
K-20 | 1 m2 Rangka jendela besi square tube (5 x 5) cm | |||||
– | Besi square tube |
M
|
4.7600
|
7,300.00
|
34,748.00
|
|
– | Besi lis kaca (1 x 1) cm |
Kg
|
4.5220
|
24,000.00
|
108,528.00
|
|
– | Pengelasan |
Cm
|
20.0000
|
2,464.00
|
49,280.00
|
|
– | Pekerja |
Oh
|
0.6500
|
42,000.00
|
27,300.00
|
|
– | Tukang kayu |
Oh
|
0.6500
|
65,000.00
|
42,250.00
|
|
– | Kepala tukang |
Oh
|
0.0650
|
75,000.00
|
4,875.00
|
|
– | Mandor |
Oh
|
0.0320
|
80,000.00
|
2,560.00
|
|
Jumlah |
269,541.00
|
|||||
Dibulatkan |
269,541.00
|
|||||
K-21 | 1 m2 Pintu lipat (folding door) bahan besi | |||||
– | Pintu lipat |
M2
|
1.0000
|
501,700.00
|
501,700.00
|
|
– | Pekerja |
Oh
|
1.0500
|
42,000.00
|
44,100.00
|
|
– | Tukang kayu |
Oh
|
1.0500
|
65,000.00
|
68,250.00
|
|
– | Kepala tukang |
Oh
|
0.1050
|
75,000.00
|
7,875.00
|
|
– | Mandor |
Oh
|
0.0052
|
80,000.00
|
416.00
|
|
Jumlah |
622,341.00
|
|||||
Dibulatkan |
622,341.00
|
|||||
K-22 | 1 m2 Tirai (venetions blinds and vertical blinds) | |||||
– | Tirai |
M2
|
1.0000
|
537,300.00
|
537,300.00
|
|
– | Pekerja |
Oh
|
0.3500
|
42,000.00
|
14,700.00
|
|
– | Tukang kayu |
Oh
|
0.3500
|
65,000.00
|
22,750.00
|
|
– | Kepala tukang |
Oh
|
0.0350
|
75,000.00
|
2,625.00
|
|
– | Mandor |
Oh
|
0.0018
|
80,000.00
|
144.00
|
|
Jumlah |
577,519.00
|
|||||
Dibulatkan |
577,519.00
|
Oleh karena analisa AHS-SNI tahun 2011, maka harga satuan bahan dan upah perlu diubah dengan harga satuan terbaru 2014, kalau koefisiennya (kolom 5) sama saja dari tahun 2007 sampai sekarang belum ada perubahan.